Town Park Plaza Paving
Estimated completion date: May 29, 2026
The Town of Dillon is set to improve the farmers market plaza area between the LaBonte and Buffalo Street parking lots in the southeast corner of Town Park. This project will include hardscaping the plaza area with concrete, landscaping, and building a new bathroom + storage building to support activities and events in the Dillon Town Park.
The construction set for the building and adjacent work won’t go out to bid until the third quarter of 2026, so the project would not be completed until June of 2027.
Town staff believes it would be beneficial for the community to go ahead and complete a majority of the concrete plaza in May of 2026 so the market attendees won’t have to walk on the loose gravel surface that presently exist this summer. Columbine Hills Construction had an opening in their May 2026 concrete schedule to complete this plaza work in May 2026.
The Scope of Work includes:
• Removing the existing gravel/millings surface down to a depth of 10”.
• Potholing of Utilities in the project area to verify actual utility depths.
• Installing conduits for future irrigation lines, electrical and other items.
• Importing and spreading 4” layer of road base beneath the new plaza area.
• Pouring a 6” concrete plaza with colored concrete and saw cutting the joints.